Information Technology: Contracting for Computer Software Development - Serious Problems Require Management Attention To Avoid Wasting Additional Millions

32,189pages on
this wiki
Add New Page
Talk0 Share

Ad blocker interference detected!


Wikia is a free-to-use site that makes money from advertising. We have a modified experience for viewers using ad blockers

Wikia is not accessible if you’ve made further modifications. Remove the custom ad blocker rule(s) and the page will load as expected.

Citation Edit

General Accounting Office, Information Technology: Contracting for Computer Software Development - Serious Problems Require Management Attention To Avoid Wasting Additional Millions (FGMSD-80-4) (Nov. 9, 1979) (full-text).

Overview Edit

Contracting for computer software can be an effective alternative to software development by federal employees. However, a review of several software development contracts found that many experience large cost overruns and lengthy delays. Certain problems were found to be common to all software contracts that had trouble.

Federal agencies contracted for software with little specific guidance. They often overestimated the stage of systems development they had reached before contracting. This overestimation often led to the issuing of inappropriate contracts using inadequate criteria for contractor performance.

Agencies overcommitted themselves and failed to control contractors through strict phasing. Management failures while the work was being done included excessive changes, failures to inspect intermediate stages of work, and failure to require progress reports from the contractor. Contractual testing requirements were often inadequate or absent. Lack of a single identified contractor source for answers and interpretation of the requirements led to communications problems. The agencies were not enforcing recovery clauses.